Concrete Slab Calculator
Enter the length, width and thickness of your slab to get the concrete in cubic yards and bags, plus the rebar and crushed-stone base for the same footprint. Add several slabs to price a patio, walkway and pad together.
Dimensions
At 2.61 cubic yards, order ready-mix: about 2.75 yd from the plant, or a truck plus a pump if access is tight.
Premixed bags
- 40 lb bags (0.3 cu ft each)
- 235
- 50 lb bags (0.375 cu ft each)
- 188
- 60 lb bags (0.45 cu ft each)
- 157
- 80 lb bags (0.6 cu ft each)
- 118
Cost estimate
- 118 × 80 lb bags
- $767.00
- Ready-mix, 2.75 yd³ ordered
- $481.25
- Wet weight
- 10,560 lb (5.28 tons)
Slab extras
- Rebar at 18" on center
- 251 linear ft
- 20 ft bars (incl. 10% laps)
- 14
- Crushed stone base, 4"
- 2.73 yd³ · 3.68 t
How the slab estimate works
The calculator multiplies length × width × thickness to get cubic feet, adds your waste allowance, and divides by 27 for cubic yards. Three more numbers come from the same footprint:
- Bags — cubic feet divided by the bag yield (0.45 cu ft for 60 lb, 0.60 cu ft for 80 lb), rounded up.
- Rebar — bars both ways at the chosen spacing, held 3 inches in from each edge, then converted to 20 ft sticks with 10% added for lap splices and offcuts.
- Gravel base — footprint × base depth, plus 15% because loose crushed stone compacts by roughly that much.
The ÷ 324 shortcut
For a slab, square feet × thickness in inches ÷ 324 gives cubic yards directly. The 324 is 12 inches per foot × 27 cubic feet per yard. A 20 × 20 ft slab at 4 inches: 400 × 4 ÷ 324 = 4.94 yd³. At 5 inches: 6.17 yd³. Each extra inch of thickness on a 400 sq ft slab costs about 1.2 more yards.
Thickened edges and uneven ground
Slabs that sit directly on the ground often have a thickened edge — a perimeter strip 8–12 inches wide poured 8–12 inches deep. Add it as a second pour using the Footing / wall shape on the concrete calculator, with the slab perimeter as its length. If your subgrade varies, measure the depth at several points and use the average; a half-inch dip across a 400 sq ft pad adds 0.6 yards.
Worked examples
192 sq ft × 4 ÷ 324 = 2.37 cubic yards, 2.61 yd with 10% extra — order 2.75 yards of ready-mix, or 118 bags of 80 lb mix. Rebar at 18 inches on center: 8 bars along the length and 11 across, 250 linear feet, or 14 twenty-foot bars with laps. A 4-inch crushed-stone base needs about 2.7 loose yards, 3.7 tons.
At 4 inches: 576 × 4 ÷ 324 = 7.11 yd³. At 6 inches: 10.67 yd³, and 11.73 yd³ with 10% extra — about 12 yards, more than a single truck on many routes, so ask the plant whether it will send two. Rebar at 18 inches: 32 bars, 752 linear feet, 42 twenty-foot sticks. Four inches of base: 8.2 yards loose, about 11 tons.
Concrete for common slab sizes
4-inch slabs (patios, walks, shed floors)
| Slab | Cubic yards | 40 lb bags | 60 lb bags | 80 lb bags |
|---|---|---|---|---|
| 8 × 10 ft | 0.99 | 89 | 60 | 45 |
| 10 × 10 ft | 1.23 | 112 | 75 | 56 |
| 10 × 12 ft | 1.48 | 134 | 89 | 67 |
| 12 × 12 ft | 1.78 | 160 | 107 | 80 |
| 12 × 16 ft | 2.37 | 214 | 143 | 107 |
| 12 × 20 ft | 2.96 | 267 | 178 | 134 |
| 14 × 20 ft | 3.46 | 312 | 208 | 156 |
| 20 × 20 ft | 4.94 | 445 | 297 | 223 |
6-inch slabs (driveways, garages)
| Slab | Cubic yards | 40 lb bags | 60 lb bags | 80 lb bags |
|---|---|---|---|---|
| 10 × 20 ft | 3.7 | 334 | 223 | 167 |
| 12 × 20 ft | 4.44 | 400 | 267 | 200 |
| 12 × 24 ft | 5.33 | 480 | 320 | 240 |
| 20 × 20 ft | 7.41 | 667 | 445 | 334 |
| 24 × 24 ft | 10.67 | 960 | 640 | 480 |
| 24 × 30 ft | 13.33 | 1200 | 800 | 600 |
Cubic yards by slab area and thickness
| Area | 4" deep | 5" deep | 6" deep |
|---|---|---|---|
| 100 sq ft | 1.23 yd³ | 1.54 yd³ | 1.85 yd³ |
| 150 sq ft | 1.85 yd³ | 2.31 yd³ | 2.78 yd³ |
| 200 sq ft | 2.47 yd³ | 3.09 yd³ | 3.7 yd³ |
| 250 sq ft | 3.09 yd³ | 3.86 yd³ | 4.63 yd³ |
| 300 sq ft | 3.7 yd³ | 4.63 yd³ | 5.56 yd³ |
| 400 sq ft | 4.94 yd³ | 6.17 yd³ | 7.41 yd³ |
| 500 sq ft | 6.17 yd³ | 7.72 yd³ | 9.26 yd³ |
| 600 sq ft | 7.41 yd³ | 9.26 yd³ | 11.11 yd³ |
| 750 sq ft | 9.26 yd³ | 11.57 yd³ | 13.89 yd³ |
| 1,000 sq ft | 12.35 yd³ | 15.43 yd³ | 18.52 yd³ |
Recommended slab thickness
| Project | Depth | Notes |
|---|---|---|
| Walkway | 4 in | 2–3 in sub-base is enough on firm soil. |
| Patio | 4 in | Over 4 in of compacted base; slope away from the house. |
| Shed floor | 4 in | 6 in or a thickened edge for a workshop with heavy tools. |
| Hot tub pad | 6 in | A filled tub with people can exceed 5,000 lb. |
| Driveway | 5–6 in | 4 in only for light cars on very stable soil. |
| Garage floor | 5–6 in | Rebar or mesh, vapor barrier under heated spaces. |
| RV or equipment pad | 6–8 in | #4 rebar at 12–16 in on center. |
| Gravel sub-base | 4–6 in | Crushed stone or road base, compacted in 2-in lifts. |
Material weights for slab work
Wet concrete is about 150 lb per cubic foot. The base materials below are sold by the ton, which is why the calculator converts the base volume to tons; for any other area, the gravel calculator does the same conversion.
| Material | lb / cu ft | lb / cu yd | tons / cu yd | Typical use |
|---|---|---|---|---|
| Gravel (general, 3/4") | 104 | 2,800 | 1.4 | Driveways, drainage, sub-base |
| Pea gravel | 100 | 2,700 | 1.35 | Paths, play areas, between pavers |
| Crushed stone (#57) | 100 | 2,700 | 1.35 | Drainage, concrete sub-base |
| Crusher run / road base | 111 | 3,000 | 1.5 | Compactable base for driveways and pavers |
| River rock | 100 | 2,700 | 1.35 | Decorative beds, dry creek beds |
| Decomposed granite | 100 | 2,700 | 1.35 | Paths and patios, compacts firm |
| Sand (dry) | 100 | 2,700 | 1.35 | Paver bedding, leveling, play sand |
| Topsoil | 81 | 2,200 | 1.1 | Lawns, raised beds, grading |
| Fill dirt | 74 | 2,000 | 1 | Filling holes and low spots |
| Compost | 37 | 1,000 | 0.5 | Soil amendment, top dressing |
| Mulch (shredded hardwood) | 22 | 600 | 0.3 | Flower beds, around trees |
| Wood chips / playground chips | 19 | 500 | 0.25 | Paths, playgrounds |
| Concrete (wet, normal weight) | 150 | 4,050 | 2.03 | 150 lb per cubic foot |
| Asphalt (hot mix, compacted) | 145 | 3,915 | 1.96 | 145 lb per cubic foot |
Related calculators
- Concrete CalculatorCubic yards and 40, 60 or 80 lb bags for slabs, footings, columns and steps.
- Gravel CalculatorCubic yards and tons of gravel, crushed stone or road base for any area.
- Mulch CalculatorHow many bags or yards of mulch for beds, rings around trees and playgrounds.
- Square Footage CalculatorArea of rooms, lots and odd shapes in sq ft, sq yd, m² and acres, with cost.
Frequently asked questions
How much concrete do I need for a 10 × 10 slab?
A 10 × 10 ft slab 4 inches thick is 100 × 4 ÷ 324 = 1.23 cubic yards, or 33.3 cubic feet. That is 56 bags of 80 lb mix or 75 bags of 60 lb mix before waste. With 10% extra, plan on 62 × 80 lb bags. At 6 inches thick the same pad needs 1.85 cubic yards.
How many bags of concrete for a 12 × 12 slab?
At 4 inches thick a 12 × 12 slab is 48 cubic feet (1.78 cubic yards): 80 bags of 80 lb mix or 107 bags of 60 lb mix, plus waste. At that size, a short-load ready-mix delivery is usually less work and costs about the same.
Does a 4 inch slab need rebar?
A 4-inch patio or walkway on well-compacted ground does not strictly need rebar; control joints and a good base matter more. Rebar (usually #3 or #4 at 18–24 inches on center) or welded wire mesh is worth adding for driveways, garage floors, slabs on clay or fill, and anything carrying a hot tub or vehicle. It holds cracks tight rather than preventing them.
How much gravel goes under a concrete slab?
Four inches of compacted crushed stone or road base is the usual sub-base for patios and garage floors; use 6 inches on clay or poorly draining soil. Order about 15% more loose stone than the finished volume, because it compacts. For a 12 × 16 ft patio, 4 inches of base is 2.37 cubic yards finished, about 2.7 yards (3.7 tons) loose.
How far apart should control joints be in a slab?
A common rule is 2 to 3 times the slab thickness in feet: 8–12 ft apart for a 4-inch slab, 10–15 ft for 6 inches. Keep the panels close to square, cut joints to a quarter of the slab depth, and cut them within a day of the pour.
How long before I can walk or drive on a new slab?